# Early finish date

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Earliest possible finish of an activity](https://pmdecoder.com/en/concept/earliest-possible-finish-of-an-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/early-finish-date-pmi/

## Definition

The early finish date, EF for short, indicates the earliest time an activity can be completed. It results from the forward pass of the critical path method: the estimated duration is added to the early start date. The logic of the network, the data date from which the calculation starts and any schedule constraints are taken into account. The early finish date of an activity in turn determines when its successors can start at the earliest. If durations, dependencies or actual progress change, it is recalculated at the next schedule update.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The early finish date corresponds to the German frühester Endzeitpunkt in network planning. Its counterpart is the late finish date, the latest finish that does not yet jeopardize the project end. The difference between the two is the total float of the activity. A planned or agreed finish date in the schedule may differ from the early finish date, for example when an activity is deliberately placed later.

## In practice

According to the schedule calculation, replacing the telephone system in a town hall can be completed on 3 June at the earliest: cabling starts on 20 May at the earliest and takes ten working days. Staff training, which builds on the finished system, therefore cannot start before 4 June. The project manager passes this information to the training team, which books its rooms accordingly.

## Frequently asked questions

### How is the early finish date calculated?

In its simplest form, by adding the duration to the early start date. Depending on the counting convention of the tool, one day is subtracted so that a one-day activity starts and finishes on the same day.

### Can the early finish date change during the project?

Yes. It is recalculated at every update and moves when predecessors finish later, durations are re-estimated or dependencies are changed.

## Related terms

- [Early finish date](https://pmdecoder.com/en/glossary/early-finish-date/)
- [Early start date](https://pmdecoder.com/en/glossary/early-start-date-pmi/)
- [Late finish date](https://pmdecoder.com/en/glossary/late-finish-date-pmi/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass-pmi/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)

---