# Duration

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Time span between start and finish of an activity](https://pmdecoder.com/en/concept/time-span-between-start-and-finish-of-an-activity/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/duration/

## Definition

In PMI usage, duration is the count of work periods an activity or an element of the work breakdown structure needs until it is complete. Non-working periods such as weekends and public holidays are not counted. Duration is usually expressed in working days or working weeks. It is estimated, for example by comparison with earlier projects, parametrically or with three values, and depends on the amount of work, the resources assigned and the underlying calendar. In the schedule it determines start and finish dates together with the dependencies.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The cross-framework term activity duration refers to the same thing. Duration is not effort: effort counts person-hours or person-days, duration the work periods that elapse. An activity requiring 20 person-days of effort can have a duration of ten days with two people. Duration differs from the calendar period in that non-working days are excluded.

## In practice

Setting up a test environment requires 15 person-days of effort. Two administrators work on it in parallel; arithmetically that would be seven and a half working days, but because coordination is needed the team plans a duration of eight working days. As a public holiday falls within the period, the activity spans almost two weeks in the calendar.

## Frequently asked questions

### How are duration and resources related?

Additional staff often shorten duration, but rarely in the same proportion. Coordination, induction and indivisible steps limit the effect. Some activities, such as drying or waiting times, cannot be shortened by resources at all.

### Why does the calendar matter?

Because durations are calculated in work periods. Only the project or resource calendar determines which days count and turns the duration into specific start and finish dates.

## Related terms

- [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/)
- [Effort](https://pmdecoder.com/en/glossary/effort/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [Project calendar](https://pmdecoder.com/en/glossary/project-calendar-pmi/)
- [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/)

---