# Dummy activity

also: Dummy arrow

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/dummy-activity/

## Definition

A dummy activity is an arrow, usually dashed, that involves no work of its own. It is used when a dependency cannot otherwise be represented in an activity-on-arrow network, for example because two activities would have the same start and end node, or because only some of the predecessors of a node apply to a particular successor. It affects the schedule calculation only through the link it creates.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A milestone is a deliberately planned event with meaning in terms of content, whereas a dummy activity is purely a means of representation. In an activity-on-node network, dummy activities are not needed because dependencies appear there directly as arrows between activities. Float is available time, whereas a dummy activity is pure logic.

## In practice

In an activity-on-arrow network for fitting out a laboratory, "Install wiring" and "Lay water pipes" end at the same node. However, setting up the laboratory cabinets depends only on the wiring, while connecting the sinks depends on both. The planner gives the water pipes their own end node, from which the sinks start, and draws a dummy activity from the end node of the wiring to it. Without this separation, the plan would wrongly show that the cabinets also wait for the water.

## Frequently asked questions

### Does a dummy activity affect dates?

Not through a duration, but through the dependency it represents. It can therefore also lie on the critical path.

### How is a dummy activity drawn?

Usually as a dashed arrow without a label or with a duration of zero.

## Related terms

- [Activity-on-arrow network](https://pmdecoder.com/en/glossary/activity-on-arrow-network/)
- [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.