# DMAIC

- Framework: [Six Sigma](https://pmdecoder.com/en/framework/six-sigma/)
- Reference: ISO 13053-1:2011
- Edition: ISO 13053-1:2011 (DMAIC methodology)
- Concept: [Defined framework for how a project proceeds](https://pmdecoder.com/en/concept/defined-framework-for-how-a-project-proceeds/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/dmaic/

## Definition

DMAIC is the core Six Sigma approach for projects that aim to improve an existing process. The letters stand for the five phases Define, Measure, Analyze, Improve and Control. First the problem, goal and scope are set; then the current performance of the process is captured with reliable data. From these data the underlying causes of variation and defects are identified before solutions are developed, tested and introduced. The last phase makes sure the improvement lasts and the process does not slip back into its old state. Each phase ends with a review, the tollgate, at which the decision to continue is taken. The approach assumes that the output of the process can be measured.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Methodology](https://pmdecoder.com/en/glossary/methodology/) | partially overlapping | Special form of a methodology, limited to projects that improve existing processes. |
| cross-framework | [Process model](https://pmdecoder.com/en/glossary/process-model/) | partially overlapping | Special form of a methodology, limited to projects that improve existing processes. |

## Classification

- Narrower terms: [Analyze phase](https://pmdecoder.com/en/glossary/analyze-phase/), [Control phase](https://pmdecoder.com/en/glossary/control-phase/), [Define phase](https://pmdecoder.com/en/glossary/define-phase/), [Improve phase](https://pmdecoder.com/en/glossary/improve-phase/), [Measure phase](https://pmdecoder.com/en/glossary/measure-phase/)

## Distinction

The PDCA cycle describes a general, repeatable learning loop; DMAIC is a project approach run through once, with defined phase results and a strong emphasis on measurement and statistics. For developing new products or processes where nothing can yet be measured, Six Sigma uses Design for Six Sigma instead, with cycles such as DMADV. Unlike a general project methodology, DMAIC is limited to improvement undertakings.

## In practice

An insurer takes an average of 19 working days to settle claims. In the Define phase the team sets a target of ten days, then measures the lead time of each processing step and finds in the analysis that missing documents trigger most of the queries. A revised checklist in the claim form is piloted and introduced; a control plan monitors lead time over the following months.

## Frequently asked questions

### How long does a DMAIC project take?

Often a few months. The duration depends on the scope; topics that are too large are better split into several projects so that results become visible within a manageable time.

### Is it allowed to return to an earlier phase?

Yes. If the analysis shows, for example, that the measurement data are insufficient, the measurement is extended. The phases set a sequence but do not rule out going back.

## Related terms

- [Tollgate](https://pmdecoder.com/en/glossary/tollgate/)
- [Design for Six Sigma](https://pmdecoder.com/en/glossary/design-for-six-sigma/)
- [PDCA cycle](https://pmdecoder.com/en/glossary/pdca-cycle/)
- [Process model](https://pmdecoder.com/en/glossary/process-model/)
- [Lean Six Sigma](https://pmdecoder.com/en/glossary/lean-six-sigma/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.