# Directing a project

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/directing-a-project/

## Definition

Directing a project describes the activities of the Project Board in PRINCE2. The process starts after start-up and runs until the project is closed. It covers the key decisions: authorizing initiation, authorizing the project after initiation, authorizing each further stage or an exception plan, giving ad hoc direction when needed and finally confirming closure. The Project Board directs by exception: it leaves the day-to-day work to the project manager and steps in when tolerances are threatened or an authorization is due. It also maintains the link to the commissioning organization.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Governance refers to the overall framework of rules and responsibilities; directing a project is the concrete sequence in which the Project Board applies that framework to one project. The process is not a body but a set of activities; the body is the Project Board. It is distinguished from the ongoing control by the project manager by its level of decision-making.

## In practice

On a project to introduce electronic files, the Project Board meets only for the end-of-stage authorizations. Between these meetings it reads the fortnightly progress reports. When the staff council unexpectedly raises concerns, the project manager asks for direction; the Executive resolves the question with the head of the authority within a week.

## Frequently asked questions

### Does the Project Board have to meet regularly?

PRINCE2 does not require fixed meetings. Decisions are taken at specific points such as the end of a stage; in between, reports and short consultations when needed are sufficient.

### Can the Project Board intervene at any time?

Yes. It can give direction without a specific trigger, for instance when priorities change in the commissioning organization. Detailed control nevertheless stays with the project manager.

## Related terms

- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Manage by exception principle](https://pmdecoder.com/en/glossary/manage-by-exception-principle/)
- [Governance](https://pmdecoder.com/en/glossary/governance/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)
- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)
- [Exception Report](https://pmdecoder.com/en/glossary/exception-report/)

---