# Dependency

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Reliance on another element](https://pmdecoder.com/en/concept/reliance-on-another-element/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Canonical version: https://pmdecoder.com/en/glossary/dependency-pmi/

## Definition

In PMI usage, a dependency is a relationship in which one element relies on another, most often between activities in the schedule. PMI distinguishes by the nature of the link: mandatory dependencies arise from the nature of the work or from contracts and regulations, for instance that a foundation has to be finished before the walls. Discretionary dependencies are based on good practice or on the team’s preferences. A further distinction is whether the dependency lies within the project or relates to something outside it, such as a permit or another project. In the schedule, dependencies are modelled as logical relationships.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Dependency](https://pmdecoder.com/en/glossary/dependency/) | equivalent | — |

## Distinction

The cross-framework term dependency refers to the same thing; this entry gives the PMI view. The precedence relationship describes the technical form, such as finish-to-start, in which a dependency is represented in the network diagram. Fast tracking is only possible for discretionary dependencies, because mandatory ones cannot be removed.

## In practice

When accounting software is being replaced, data migration can only begin once the new system has been installed; this is a mandatory dependency. That training takes place only after data migration, on the other hand, is something the team simply decided so that people can practise with real data. When time runs short, the project manager brings the training forward using test data. In addition, the project has an external dependency on the tax advisers approving the new chart of accounts.

## Frequently asked questions

### Why does the type of dependency matter?

Because it shows where the schedule can be changed. Discretionary dependencies can be removed if necessary, mandatory ones cannot. External dependencies are outside the team’s control and deserve particular attention.

### How do you keep track of external dependencies?

Record them with owners and dates, agree them with the parties outside the project and often treat them as a risk at the same time, because the project relies on commitments made by others.

## Related terms

- [Dependency](https://pmdecoder.com/en/glossary/dependency/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking-pmi/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.