# Deliverables Acceptance Management Plan

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 6.6
- Edition: PM² Guide 3.1
- Concept: [Criteria for a finished result](https://pmdecoder.com/en/concept/criteria-for-a-finished-result/)
- Topic area: [Scope and requirements](https://pmdecoder.com/en/area/scope-and-requirements/)
- Canonical version: https://pmdecoder.com/en/glossary/deliverables-acceptance-management-plan/

## Definition

In PM², the Deliverables Acceptance Management Plan is intended to ensure that a project's results are accepted by the customer and that the acceptance process itself uses resources efficiently. It documents the agreed acceptance criteria, the approach and the individual steps, the responsibilities, the effort required and the requirements regarding timing and content. This allows the requestor side to accept the deliverables formally on the basis of objective criteria and within a time frame agreed in advance. The Project Manager prepares the plan, the Business Manager reviews the requirements and the Project Steering Committee approves it.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria-pmi/) | partially overlapping | plan that, in addition to the criteria, also defines the steps, responsibilities and dates of acceptance |
| Scrum | [Definition of Done](https://pmdecoder.com/en/glossary/definition-of-done/) | partially overlapping | serves as the quality standard for every Increment of a product, not for an individual deliverable |
| cross-framework | [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria/) | partially overlapping | plan that, in addition to the criteria, also defines the steps, responsibilities and dates of acceptance |

## Distinction

Acceptance criteria state how a result is measured; the Deliverables Acceptance Management Plan additionally specifies who accepts what, when and how. An acceptance record, by contrast, documents the outcome of an acceptance that has actually taken place.

## In practice

For a new application form, the plan specifies that the User Representatives test twenty prepared cases over two weeks, that at least nineteen must run without errors and that critical defects are fixed within five days. The Business Manager and the Project Owner are authorized to sign.

## Frequently asked questions

### When is the Deliverables Acceptance Management Plan prepared?

In the Planning Phase, so that criteria and approach are settled before the deliverables are produced.

### Does the plan also allow provisional acceptance?

Yes. It can specify that results are first accepted provisionally and then finally after a probation period; the Ready for Closing phase gate also relies on this.

## Related terms

- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)
- [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria/)
- [Ready for Closing](https://pmdecoder.com/en/glossary/ready-for-closing/)
- [Executing Phase](https://pmdecoder.com/en/glossary/executing-phase/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)

---