# Define phase

- Framework: [Six Sigma](https://pmdecoder.com/en/framework/six-sigma/)
- Reference: ISO 13053-1:2011
- Edition: ISO 13053-1:2011 (DMAIC methodology)
- Concept: [Opening stage of a project](https://pmdecoder.com/en/concept/opening-stage-of-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Canonical version: https://pmdecoder.com/en/glossary/define-phase/

## Definition

The Define phase clarifies which problem the improvement project is to solve, why it is worthwhile and how success will be measured. The team outlines the affected process in broad steps, usually with a SIPOC, and draws the line between what belongs to the project and what does not. Customer requirements are gathered and translated into measurable characteristics that are critical to quality. The result is an agreed project charter with problem statement, goal, scope, team, outline timeline and expected benefit. The tollgate at the end of the phase decides whether the project moves on to measurement.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Initiating a project](https://pmdecoder.com/en/glossary/initiating-a-project/) | closely related | Forms the first management stage and ends with authorization of the project by the Project Board; the pre-project check comes before it. |
| PM² | [Initiating Phase](https://pmdecoder.com/en/glossary/initiating-phase/) | closely related | ends with the Ready for Planning phase gate and delivers the Business Case and Project Charter |
| cross-framework | [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/) | closely related | First phase of an improvement project; more narrowly focused on the problem, a measurable output and customer requirements than general initiation. |
| PRINCE2 | [Starting up a project](https://pmdecoder.com/en/glossary/starting-up-a-project/) | partially overlapping | Short pre-project check; initiation follows as a separate process. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [DMAIC](https://pmdecoder.com/en/glossary/dmaic/)

## Distinction

In purpose the Define phase corresponds to project initiation in other approaches, but it is more narrowly focused on a process problem and its measurable output. Unlike the PM² Initiating Phase, it explicitly includes translating customer statements into measurable characteristics. Detailed project planning with schedule and resource planning is not the main concern.

## In practice

A hospital wants to shorten waiting times in its emergency department. In the Define phase the team decides to measure the time from registration to first assessment by a physician and excludes inpatient admission from the scope. Conversations with patients and ambulance services show which waiting time is considered acceptable. The champion signs the project charter at the tollgate.

## Frequently asked questions

### What is the most important result of the Define phase?

A clear project charter with measurable statements that the team and champion both support. It protects the project from growing out of bounds later on.

### Is the problem statement changed later?

It happens. If the data from the Measure phase paint a different picture, the project charter is adjusted and agreed again.

## Related terms

- [Six Sigma project charter](https://pmdecoder.com/en/glossary/six-sigma-project-charter/)
- [SIPOC](https://pmdecoder.com/en/glossary/sipoc/)
- [Voice of the Customer](https://pmdecoder.com/en/glossary/voice-of-the-customer/)
- [Critical to Quality](https://pmdecoder.com/en/glossary/critical-to-quality/)
- [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/)

---