# Defects per Million Opportunities

abbr. DPMO

- Framework: [Six Sigma](https://pmdecoder.com/en/framework/six-sigma/)
- Reference: ISO 13053-1:2011
- Edition: ISO 13053-1:2011 (DMAIC methodology)
- Canonical version: https://pmdecoder.com/en/glossary/defects-per-million-opportunities/

## Definition

Defects per Million Opportunities, DPMO for short, relates the number of defects counted to the number of occasions on which a defect could have occurred: defects divided by the product of units inspected and defect opportunities per unit, multiplied by one million. This makes processes comparable whose outputs have different numbers of points at which something can go wrong. DPMO can be converted into a sigma level; the well-known Six Sigma target of 3.4 defects per million opportunities is based on this conversion and on a customary assumption about the long-term shift of the process.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A simple defect rate counts defective units; a unit with three defects counts once there. DPMO, by contrast, counts each individual defect and relates it to the opportunities. The figure “ppm” usually denotes defective parts per million parts and is therefore not the same.

## In practice

An accounts department checks 1,000 incoming invoices, each with five data items that must be captured correctly, such as amount, date and cost centre. It finds 40 errors. This gives 40 divided by 5,000 opportunities, that is 8,000 DPMO, which corresponds to a sigma level of about 3.9 under the usual conversion.

## Frequently asked questions

### How are defect opportunities defined?

As characteristics that matter to the customer and where defects can actually occur. Counting an artificially high number of opportunities improves the figure without the process getting better.

### Is DPMO suitable for every process?

It works best for results that can be counted as defect-free or defective. For measurable quantities such as times or dimensions, variation and process capability are often examined directly.

## Related terms

- [Sigma level](https://pmdecoder.com/en/glossary/sigma-level/)
- [Critical to Quality](https://pmdecoder.com/en/glossary/critical-to-quality/)
- [Measure phase](https://pmdecoder.com/en/glossary/measure-phase/)
- [Specification limit](https://pmdecoder.com/en/glossary/specification-limit/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
