# Decomposition

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.19
- Edition: ISO 21506:2024
- Concept: [Stepwise division into smaller units](https://pmdecoder.com/en/concept/stepwise-division-into-smaller-units/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/decomposition/

## Definition

In decomposition, the overall result of a project or programme is divided into partial results and tasks until units emerge that can be reliably estimated, assigned and monitored. This does not happen just once at the start but repeatedly over the life cycle, as more details become known. The breakdown can be hierarchical, by function or according to other criteria such as phases or locations. The typical outcome is a work breakdown structure with work packages at the lowest level.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Decomposition](https://pmdecoder.com/en/glossary/decomposition-pmi/) | equivalent | — |

## Distinction

Decomposition is the activity; a work breakdown structure is a typical result, and hierarchical decomposition is the form that produces it. Unlike sequencing, decomposition does not answer the question of the order in which work is done, only what the whole consists of. Agile approaches break things down in a similar way, for example from themes to larger requirements to individual tasks, but usually only shortly before implementation.

## In practice

For an international professional congress, the team first breaks the undertaking down into programme, venue, participant management, sponsorship, communication and follow-up. Participant management is further divided into registration system, invoicing, hotel allocations and name badges. In the process, it becomes apparent that nobody had thought of invitation letters for the visa applications of guests from outside the EU. The task is added as a separate work package.

## Frequently asked questions

### How far should you break things down?

Until a unit can be reliably estimated and assigned to a responsible person. A common rule of thumb is work packages lasting from a few days to a few weeks.

### What mistakes are common in decomposition?

Tasks and results get mixed up, cross-cutting work such as testing or project management is forgotten, or the breakdown becomes so detailed that nobody can maintain it.

## Related terms

- [Hierarchical decomposition](https://pmdecoder.com/en/glossary/hierarchical-decomposition/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Project scope](https://pmdecoder.com/en/glossary/project-scope/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.