## Definition

In decision tree analysis, a tree starts with a decision from which branches lead to the possible alternatives. At chance nodes, these branch further into possible events with their probabilities. At the end of each path is an outcome, such as cost or profit. Rolling back from the end to the root gives an expected value for each alternative, which makes them comparable.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Expected monetary value is the calculated figure; the decision tree is the representation in which it is determined for multi-stage decisions. An influence diagram shows the relationships between decisions, uncertainties and objectives more compactly, but without all the individual paths. Weighted scoring (Nutzwertanalyse) compares alternatives against several weighted criteria without taking probabilities into account.

## In practice

A software company is considering whether to adapt an existing platform for a customer project or to develop a new one. Adaptation costs 200,000 euros, with a 30 per cent probability of an additional 150,000 euros for modifications. New development costs 300,000 euros, with a 20 per cent probability of a further 50,000 euros. The tree gives expected costs of 245,000 euros for adaptation and 310,000 euros for new development. The team opts for adaptation and monitors the modification risk closely.

## Frequently asked questions

### When is a decision tree suitable?

When a decision has a few clear alternatives whose consequences depend on uncertain events, and probabilities and values can be estimated at least roughly.

### Should you always choose the alternative with the best expected value?

Not necessarily. Anyone who cannot bear a large loss may choose an alternative with a worse expected value but a smaller spread.

## Related terms

- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value/)
- [Influence diagram](https://pmdecoder.com/en/glossary/influence-diagram/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.