# Decision tree analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Evaluating decisions under uncertainty as a tree](https://pmdecoder.com/en/concept/evaluating-decisions-under-uncertainty-as-a-tree/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/decision-tree-analysis-pmi/

## Definition

In PMI usage, decision tree analysis is a technique for choosing between several alternatives when their outcomes depend on uncertain events. The tree starts with a decision node from which the alternatives branch out. Each branch is followed by chance nodes with the possible events, their probabilities and their financial or time consequences. Costs and returns are totalled for each path; working from right to left, the expected monetary value is then calculated for each chance node. According to this logic, the alternative with the most favourable expected value is the best. PMI assigns the technique to quantitative analysis in risk management, but it is also suitable for other decisions under uncertainty.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The PMI name means the same as the cross-framework term Entscheidungsbaumanalyse. Expected monetary value is the measure used to evaluate the tree, not the technique itself. A Monte Carlo simulation, by contrast, considers many uncertainties at once and produces distributions rather than one expected value per alternative.

## In practice

A manufacturer must decide whether to carry out a preliminary certification costing 40,000 euros for a new device. Without the preliminary check, experts estimate a 30 percent probability of failing approval, which would cost 250,000 euros in rework. With the check, the probability drops to five percent. The decision tree yields expected costs of 75,000 euros without and 52,500 euros with the check; the team recommends the check.

## Frequently asked questions

### Where do the probabilities in the decision tree come from?

From historical data where available, otherwise from structured expert estimates. Because the result depends heavily on them, it is worth checking at which probability the recommendation changes.

### Does decision tree analysis take risk appetite into account?

Not in its simple form, because it only compares expected values. An organization that wants to avoid large losses at all costs may choose the safer alternative despite a worse expected value. This should then be justified explicitly.

## Related terms

- [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis/)
- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.