# Data date

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Reference date for recorded project status](https://pmdecoder.com/en/concept/reference-date-for-recorded-project-status/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/data-date/

## Definition

At PMI, the data date is the reference point in time for which the project's status is captured and evaluated. In the schedule it separates the past, for which actual data such as actual start and finish dates or percentages of completion are entered, from the future, which continues to be planned and forecast. All indicators in a report, such as earned value, actual cost and planned value, refer to the same data date. Other common English terms are status date or as-of date.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Status date](https://pmdecoder.com/en/glossary/status-date/) | equivalent | — |

## Distinction

The concept is described in the glossary under the cross-framework term “Stichtag” (data date); the PMI term is equivalent. The data date is not the date on which the report is prepared or distributed; the two are often a few days apart. Nor is it a milestone or a contractual deadline.

## In practice

A project team updates its schedule every Friday with a data date of 6 p.m. By then, team members report actual dates and remaining durations. On Monday the project manager distributes the report. An activity completed on Sunday therefore only appears as finished in the following week’s evaluation.

## Frequently asked questions

### Why is a uniform data date needed?

Only if all figures describe the same status can cost, performance and schedule be compared. Different cut-off dates distort indicators and forecasts.

### What happens to activities before the data date that are not finished?

Their remaining work is moved beyond the data date. Scheduling tools usually do this automatically when updating, so that the schedule shows no unfinished work in the past.

## Related terms

- [Status date](https://pmdecoder.com/en/glossary/status-date/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)
- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)
- [Forecast](https://pmdecoder.com/en/glossary/forecast/)

---