# Daily Scrum

- Framework: [Scrum](https://pmdecoder.com/en/framework/scrum/)
- Reference: Scrum Guide 2020, Abschnitt Daily Scrum
- Edition: Scrum Guide 2020
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/daily-scrum/

## Definition

In the Daily Scrum, the Developers meet every day for at most 15 minutes. So that the meeting requires little organization, it always takes place at a fixed time and in a fixed location on each working day. The Developers look at how far they have progressed towards the Sprint Goal and adjust the Sprint Backlog where necessary. How they structure the meeting is up to them, as long as it ends with a concrete, actionable plan for the day ahead. The Product Owner or the Scrum Master take part as Developers if they have taken on work from the Sprint Backlog themselves.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Scrum Event](https://pmdecoder.com/en/glossary/scrum-event/)

## Distinction

The Daily Scrum is not a status report to a manager but coordination among the Developers. Stand-up meetings in other teams often follow similar formats but do not relate to a Sprint Goal. The three questions about yesterday, today and impediments, formerly given as an example, have no longer been part of the Scrum Guide since 2020.

## In practice

A team developing a maintenance app for lifts meets every morning at 9.15 a.m. in front of its digital board. Instead of reporting in turn, the Developers go through the items from right to left and ask what is preventing their completion. On Tuesday it becomes clear that the connection to the spare parts warehouse is stuck. Two Developers agree to tackle it together directly after the meeting.

## Frequently asked questions

### May the Product Owner attend the Daily Scrum?

The event is intended for the Developers. If the Product Owner takes on work from the Sprint Backlog, he or she takes part as a Developer; otherwise attendance is not foreseen.

### Is the Daily Scrum the only opportunity to adjust the plan?

No. The Developers can coordinate and replan at any time. The Daily Scrum simply ensures that this happens at least once a day.

## Related terms

- [Sprint Backlog](https://pmdecoder.com/en/glossary/sprint-backlog/)
- [Sprint Goal](https://pmdecoder.com/en/glossary/sprint-goal/)
- [Developer](https://pmdecoder.com/en/glossary/developer/)
- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)

## Differences from other editions

- Scrum Guide 2017: The Daily Scrum was an internal meeting of the Development Team, and the Scrum Master made sure it took place. As one possible structure, the guide suggested that each member report on their contribution to the Sprint Goal since the previous meeting, their plans until the next one and any obstacle they saw.

---