# Daily Log

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Managementprodukte
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/daily-log/

## Definition

In PRINCE2 the Daily Log is the Project Manager’s personal working record. It captures what comes up in day-to-day project work and does not need a register of its own: minor problems and queries the Project Manager can resolve personally, agreed actions with owner and due date, notable events and observations. It is the first log to be created in a PRINCE2 project, because it is already used during start-up, before the other registers are set up in initiation. Until then it also holds risks and issues, which are later transferred to the formal registers. No fixed structure is prescribed; typical columns are date, entry, person responsible, target date and result.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The Daily Log complements the Issue Register and the Risk Register: what has to be assessed, decided and tracked belongs there; what can be dealt with informally stays in the Daily Log. Unlike meeting minutes, it is not tied to a meeting but accompanies the project continuously. The Lessons Log, by contrast, deliberately collects experience that is of value beyond the day.

## In practice

The project manager for moving an administration into a new building notes in the Daily Log that the facility manager wants to bring the key handover forward by two days, and records that she will agree this with the removal company. She closes the entry the following day. When it becomes clear that the fire safety inspection of the new floor is still outstanding and could delay the move, she transfers the matter to the Issue Register, because it requires a formal decision.

## Frequently asked questions

### Who may write in the Daily Log?

It is the Project Manager’s record. Entries can be made by project support, but the Project Manager remains responsible for the content. Other people report their points to the Project Manager.

### When is the Daily Log created?

During start-up, as soon as a Project Manager has been appointed. In this early period it therefore also serves as a provisional place for risks and issues.

## Related terms

- [Issue Register](https://pmdecoder.com/en/glossary/issue-register-prince2/)
- [Risk Register](https://pmdecoder.com/en/glossary/risk-register-prince2/)
- [Meeting minutes](https://pmdecoder.com/en/glossary/meeting-minutes/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Lessons Log](https://pmdecoder.com/en/glossary/lessons-log/)
- [Project Manager (PRINCE2)](https://pmdecoder.com/en/glossary/project-manager-prince2/)
- [Starting up a project](https://pmdecoder.com/en/glossary/starting-up-a-project/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.