# Critical path

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.18
- Edition: ISO 21506:2024
- Concept: [Longest sequence of activities without float](https://pmdecoder.com/en/concept/longest-sequence-of-activities-without-float/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/critical-path/

## Definition

The critical path is the longest route from start to finish through a network schedule. Every activity on it has zero total float, provided the target date matches the result of the forward pass. If an activity on this path is delayed, the whole project is delayed; if it is shortened, the project can finish earlier until another path becomes critical. A network schedule can have several critical paths at once.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Each individual activity on this path is a critical activity. The critical path method is the calculation procedure that determines it. In critical chain project management, it is replaced by the critical chain, which also takes resource constraints into account.

## In practice

In the refurbishment of a wastewater treatment plant, the critical path consists of the permit, the tender for the mechanical equipment, delivery of the blowers, installation and trial operation; the construction work itself has float. The project manager therefore does not put pressure on the building contractors but negotiates a shorter delivery time with the blower manufacturer. Afterwards the software shows that the concrete work is now on the critical path.

## Frequently asked questions

### Why can the critical path change?

Because activities run faster or slower than planned. A path with little float becomes critical as soon as that float has been used up.

### Are activities off the critical path unimportant?

No. They have leeway in time but are often just as important in content and can themselves become critical if they are delayed.

## Related terms

- [Critical activity](https://pmdecoder.com/en/glossary/critical-activity/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)
- [Total float](https://pmdecoder.com/en/glossary/total-float/)
- [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/)

---