# Critical path method

abbr. CPM

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Calculation method for dates and float](https://pmdecoder.com/en/concept/calculation-method-for-dates-and-float/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/critical-path-method/

## Definition

The critical path method works with fixed activity durations that are assumed to be known. A forward pass determines the earliest dates and a backward pass the latest; comparing them yields float and the critical path. The method was developed in the United States in the late 1950s for planning construction and maintenance projects in industry. To this day it forms the calculation core of most scheduling programs.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

PERT, which emerged at about the same time, works with three estimates per activity and makes statements about probabilities. The critical chain method adds resource bottlenecks and pooled buffers. The critical path is the result, the critical path method the procedure.

## In practice

A chemical company plans the annual shutdown of a production plant for maintenance work; every day of shutdown costs a great deal of money. The planners record around 600 maintenance activities with durations and dependencies and let the software do the calculation. The critical path runs through the replacement of a heat exchanger. For this, spare parts are provided in advance and round-the-clock shifts are planned, while non-critical work takes place during the day.

## Frequently asked questions

### What does the abbreviation CPM stand for?

For critical path method, the English name of the method, which in German is called Methode des kritischen Wegs.

### What are the limits of the method?

It assumes fixed durations and takes into account neither uncertainty nor scarce resources. Complementary approaches such as PERT, simulations and resource levelling exist for this purpose.

## Related terms

- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)
- [Network planning technique](https://pmdecoder.com/en/glossary/network-planning-technique/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass/)
- [Critical chain method](https://pmdecoder.com/en/glossary/critical-chain-method/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.