# Critical path method

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Calculation method for dates and float](https://pmdecoder.com/en/concept/calculation-method-for-dates-and-float/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/critical-path-method-pmi/

## Definition

The critical path method, CPM for short, is the standard technique for calculating dates from a network of activities. It is based on the activities, their estimated durations and the logical relationships between them. The forward pass determines the early start and finish dates, the backward pass the late dates. The difference yields total float and free float, and the activities without flexibility form the critical path. The method thus shows the shortest possible project duration and where scheduling has room to move. It was developed in industry in the late 1950s.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

In German the technique is called Methode des kritischen Wegs. The critical path method works with a single duration per activity; PERT, by contrast, uses three estimates and thereby reflects uncertainty. The critical chain method builds on similar logic but takes resource constraints into account and plans pooled buffers. The precedence diagramming method describes how the network is drawn; CPM describes how to calculate within it.

## In practice

An organizer is planning a professional conference with 40 activities, from selecting speakers to printing the programme. After durations and dependencies have been entered, the scheduling tool calculates according to the critical path method and shows that the conference can take place in 22 weeks at the earliest. The desired date is 20 weeks away; from the negative float, the project manager immediately sees which activities must be accelerated.

## Frequently asked questions

### Is a scheduling tool needed for the critical path method?

Small networks can be calculated by hand or in a spreadsheet. With many activities and frequent changes, a tool is practically indispensable because it recalculates the dates at every update.

### Does the critical path method take resources into account?

Not directly. The calculation assumes unlimited resources. Constraints are then handled with techniques such as resource leveling, which can change the critical path.

## Related terms

- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)
- [Forward pass](https://pmdecoder.com/en/glossary/forward-pass-pmi/)
- [Backward pass](https://pmdecoder.com/en/glossary/backward-pass-pmi/)
- [Precedence diagramming method](https://pmdecoder.com/en/glossary/precedence-diagramming-method/)
- [Network planning technique](https://pmdecoder.com/en/glossary/network-planning-technique/)

---