# Critical chain method

also: Critical chain project management · abbr. CCPM

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Scheduling with aggregated buffers](https://pmdecoder.com/en/concept/scheduling-with-aggregated-buffers/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/critical-chain-method/

## Definition

The critical chain method goes back to Eliyahu M. Goldratt, who derived it from his theory of constraints in the late 1990s. Activities are planned with tight but realistic durations without built-in safety margins. Some of the reserves removed in this way are placed at the end as a project buffer and inserted as feeding buffers where side chains join the critical chain. Control is based on the consumption of these buffers in relation to progress.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Critical chain method](https://pmdecoder.com/en/glossary/critical-chain-method-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The critical path method determines the longest path without regard to resources; the critical chain is the longest path taking resource conflicts into account. Unlike conventional float, which results from the calculation, the buffers here are deliberately set and managed jointly. The method regards multitasking as a major cause of delays that should be avoided.

## In practice

A manufacturer of measuring instruments switches its development projects to critical chain. Instead of giving each work package a safety allowance, the teams estimate the duration that is sufficient in about half of all cases, and the project management places a shared project buffer at the end. A traffic light shows how much buffer has been consumed relative to progress. The teams also work on only one task at a time, and lead times fall noticeably in the first year.

## Frequently asked questions

### Why should safety margins be removed from the activities?

Because experience shows that hidden reserves get used up whether they are needed or not, for example because work is put off until the last moment. A shared buffer is easier to control.

### What is a fever chart?

A chart that compares buffer consumption with project progress and is divided into green, yellow and red zones.

## Related terms

- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)
- [Float](https://pmdecoder.com/en/glossary/float/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.