# Critical chain method

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Scheduling with aggregated buffers](https://pmdecoder.com/en/concept/scheduling-with-aggregated-buffers/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/critical-chain-method-pmi/

## Definition

The critical chain method is a scheduling approach that considers the availability of scarce resources as well as logical dependencies. The longest chain of activities resulting from logic and resource constraints is called the critical chain. Activity durations are estimated tightly, without the safety margins that are otherwise built into each individual estimate. That reserve is pooled instead: as a project buffer at the end of the critical chain and as feeding buffers where other paths join the critical chain. Control is based on how much buffer has been consumed relative to progress. The method goes back to Eliyahu M. Goldratt and is based on his theory of constraints.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Critical chain method](https://pmdecoder.com/en/glossary/critical-chain-method/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The critical chain method corresponds to the German Methode der kritischen Kette. The critical path method initially looks only at logic and deals with resources in a separate step; its float is calculated flexibility of individual activities. In critical chain, buffers are deliberately planned and managed reserves. A schedule buffer in the general sense is any planned time reserve, whatever the method.

## In practice

In product development at a device manufacturer, the test laboratory is a bottleneck shared by several projects. The project manager plans the laboratory tests as part of the critical chain, cuts the teams' estimates to realistic values without margins and places a four-week project buffer before the launch date. The weekly meetings then focus on just two questions: how much buffer has been used, and how much work on the chain is still open.

## Frequently asked questions

### Why is safety time removed from individual estimates?

Experience shows that distributed reserves are often lost, because work expands to fill the available time or is started late. A shared buffer balances delays and early finishes of individual activities and can therefore be smaller overall.

### When is the critical chain method suitable?

Mainly when a few scarce resources determine the flow of work, such as specialists, test rigs or equipment, and when those involved are willing to work with tight estimates and open buffer monitoring.

## Related terms

- [Critical chain method](https://pmdecoder.com/en/glossary/critical-chain-method/)
- [Theory of Constraints](https://pmdecoder.com/en/glossary/theory-of-constraints/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)
- [Schedule buffer](https://pmdecoder.com/en/glossary/schedule-buffer/)
- [Resource leveling](https://pmdecoder.com/en/glossary/resource-leveling/)

---