# Critical activity

also: Critical task

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Activity without scheduling flexibility](https://pmdecoder.com/en/concept/activity-without-scheduling-flexibility/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/critical-activity/

## Definition

A critical activity lies on the critical path and has a total float of zero or less. Every extension and every later start moves the end date, unless another activity makes up the time. Critical activities are therefore monitored particularly closely during project control, staffed with experienced people and given priority when risks are addressed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Critical path activity](https://pmdecoder.com/en/glossary/critical-path-activity/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The critical path is the chain; the critical activity is a link in it. Near-critical activities have only little float, for example less than five working days, and are often highlighted too, because they can quickly become critical. An activity can, however, be important or risky in terms of content regardless of its float.

## In practice

In the schedule for a software roll-out, the project management marks all critical activities in red and all those with less than five days of float in orange. In the weekly meeting, only these activities are discussed individually. When the interface programming, marked in red, is two days behind, a second developer is brought in. The data cleansing, marked in orange, moves into the red zone itself after a delay of its own.

## Frequently asked questions

### How are critical activities identified?

Through the schedule calculation: activities with a total float of zero or less are critical. Scheduling tools usually mark them automatically.

### What is a near-critical activity?

An activity whose float lies below a defined threshold. The project itself determines where this threshold lies.

## Related terms

- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)
- [Total float](https://pmdecoder.com/en/glossary/total-float/)