# Crashing

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Shortening through additional resources](https://pmdecoder.com/en/concept/shortening-through-additional-resources/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/crashing-pmi/

## Definition

In PMI usage, crashing is a schedule compression technique that shortens the duration of a schedule by adding resources, specifically where the reduction costs least. Examples are overtime, additional staff, extra equipment or expedited deliveries at a premium. Crashing is only effective for activities on the critical path, because only shortening these brings the project end forward. It usually increases cost and only works if more resources actually speed up the work.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Crashing](https://pmdecoder.com/en/glossary/crashing/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression-pmi/)

## Distinction

The cross-framework entry on crashing describes the same technique; here the focus is on its place in PMI terminology, which treats crashing as a form of schedule compression. Fast tracking, in contrast, shortens the schedule by overlapping activities and mainly increases risk rather than cost.

## In practice

A construction project is at risk of missing the contractually agreed handover by two weeks. The project manager examines the critical activities and finds that a second crew would shorten interior finishing by ten days at an extra cost of 18,000 euros. A weekend shift for the screed saves another four days for 6,000 euros. Because the contractual penalty would be higher, both measures are implemented.

## Frequently asked questions

### When is crashing worthwhile?

When the benefit of finishing earlier, such as avoided penalties or earlier revenue, exceeds the additional cost. To decide, the extra cost per day gained is compared across the critical activities.

### What are the limits of crashing?

Not all work gets faster with more people. Induction and coordination take time, and some tasks cannot be divided. In addition, the critical path may shift, so that further reductions have no effect.

## Related terms

- [Crashing](https://pmdecoder.com/en/glossary/crashing/)
- [Fast tracking](https://pmdecoder.com/en/glossary/fast-tracking-pmi/)
- [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression-pmi/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)
- [Brooks's law](https://pmdecoder.com/en/glossary/brooks-law/)

---