# Cost variance

abbr. CV

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.17
- Edition: ISO 21506:2024
- Concept: [Difference between earned value and actual cost](https://pmdecoder.com/en/concept/difference-between-earned-value-and-actual-cost/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/cost-variance/

## Definition

Cost variance indicates how economically a project or programme has worked so far: it shows whether the work done has cost more or less than was budgeted for it. In earned value management it is calculated as earned value minus actual cost. A negative value means that more was spent on the work than intended, a positive value that it was done more cheaply. It is often also given as a percentage of earned value to put it into perspective.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Cost variance](https://pmdecoder.com/en/glossary/cost-variance-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A simple comparison of planned and actual costs at a given date mixes up cost and schedule variances: a project that has done less has usually also spent less. Cost variance based on earned value avoids this error because it relates costs to the work actually performed. Variance at completion, by contrast, compares the total budget with the forecast total cost.

## In practice

A machine builder is constructing a special-purpose plant. At the end of the month, assemblies with a budget of 420,000 euros are complete, but they have cost 465,000 euros. The cost variance is minus 45,000 euros, or about minus eleven per cent. Analysis by work package shows that almost all of the variance comes from the control engineering, where expensive rework was needed. The other assemblies are within budget.

## Frequently asked questions

### Is a positive cost variance always good?

Usually, yes. However, it can also point to overly generous estimates or to costs that have not yet been booked, which should be checked.

### When is action needed?

When the variance exceeds agreed tolerances or keeps growing over several reporting periods.

## Related terms

- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost/)
- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)

---