# Cost variance

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Difference between earned value and actual cost](https://pmdecoder.com/en/concept/difference-between-earned-value-and-actual-cost/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/cost-variance-pmi/

## Definition

Cost variance, abbreviated CV, indicates in PMI’s earned value method by how much the work performed was more or less expensive than budgeted. It is calculated by subtracting actual cost from earned value. A negative value means an overrun, a positive value an underrun and zero an exact match. The CV can be determined for a reporting period or cumulatively and always applies as of the data date. At project completion it equals the difference between the budget at completion and the actual total cost.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

“Kostenabweichung” (cost variance) according to ISO 21506, the lead term of the concept in the glossary, is equivalent. Cost variance is an absolute value; the cost performance index relates the same quantities as a ratio. Schedule variance compares earned value with planned value, and variance at completion looks ahead to the expected end of the project.

## In practice

For the conversion of a canteen, the work package “ventilation” is budgeted at 50,000 euros and half complete. Earned value is therefore 25,000 euros, while 31,000 euros has been paid so far. Cost variance is minus 6,000 euros. The site management finds that more expensive fire dampers were installed and clarifies whether these extra costs are covered by the client’s budget.

## Frequently asked questions

### Why compare costs with earned value rather than planned value?

Because planned value contains the scheduled progress. Comparing it with costs would mix delay and overrun. Earned value credits exactly the work for which the costs were incurred.

### How meaningful is cost variance on its own?

Of limited value. The same amount weighs more heavily in a small project than in a large one. It is therefore usually considered together with the cost performance index and percentage thresholds.

## Related terms

- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)
- [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index-pmi/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance-pmi/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion-pmi/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.