# Cost-reimbursable contract

also: Cost-plus contract, Cost-reimbursement contract

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Contract reimbursing actual costs](https://pmdecoder.com/en/concept/contract-reimbursing-actual-costs/)
- Topic area: [Contracts and procurement](https://pmdecoder.com/en/area/contracts-and-procurement/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/cost-reimbursable-contract/

## Definition

Under a cost-reimbursable contract, the contractor bills its documented costs and receives a mark-up on them. This can be agreed as a fixed amount, as a percentage of costs or as a performance-related incentive, for example a bonus if a target cost is undercut. The cost risk lies mainly with the client, who therefore demands insight into the costs and a say in major decisions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Contract](https://pmdecoder.com/en/glossary/contract/)

## Distinction

The fixed-price contract shifts the cost risk to the contractor, the cost-reimbursable contract to the client. Under a time and materials contract, hours and materials are charged at agreed rates without the underlying costs being disclosed. A percentage mark-up on costs is considered problematic, because higher costs then also mean higher profit; some public procurement rules, for example in the USA, therefore do not permit this form.

## In practice

A pharmaceutical company commissions a research institute to develop a manufacturing process whose effort nobody can estimate reliably. The parties agree on cost reimbursement with a fixed fee and a bonus if certain yield values are achieved. The institute submits time and material records every month, and the company sits on the steering committee. After a year, the contract is converted to a fixed price for the transfer into production.

## Frequently asked questions

### When does a cost-reimbursable contract make sense?

When the scope cannot be reliably described at the outset, for example in research, development or urgent refurbishments where the condition of the structure is unclear.

### How does the client protect itself against escalating costs?

Through cost ceilings, incentives for savings, audit rights, regular reports and approvals before major expenditure.

## Related terms

- [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract/)
- [Time and materials contract](https://pmdecoder.com/en/glossary/time-and-materials-contract/)

---