# Cost-reimbursable contract

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Contract reimbursing actual costs](https://pmdecoder.com/en/concept/contract-reimbursing-actual-costs/)
- Topic area: [Contracts and procurement](https://pmdecoder.com/en/area/contracts-and-procurement/)
- Canonical version: https://pmdecoder.com/en/glossary/cost-reimbursable-contract-pmi/

## Definition

Under a cost-reimbursable contract, the seller receives from the buyer the costs actually incurred and allowable under the contract. In addition, there is a fee that represents the seller’s profit. PMI distinguishes common forms: cost plus fixed fee with a fixed fee, cost plus incentive fee with a fee that depends on meeting agreed cost or performance targets, and cost plus award fee, where the buyer determines the fee based on its assessment of performance. This contract type is suitable when the scope is uncertain at the outset or likely to change significantly.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The PMI term is equivalent to the concept described in the glossary under “Kostenerstattungsvertrag” (cost-reimbursable contract). Under a fixed-price contract the seller bears the cost risk, under a cost-reimbursable contract mainly the buyer. The time and materials contract lies in between and charges agreed rates for time and materials.

## In practice

A research institute commissions a specialist firm to build a prototype whose technical solution is still open. The parties agree on reimbursement of documented costs plus a fixed fee. The client requires monthly cost reports with receipts and reserves the right to audit the accounts in order to check that the costs are allowable.

## Frequently asked questions

### What risk does the buyer bear under a cost-reimbursable contract?

The buyer bears the risk of rising costs, because all allowable costs are reimbursed. It therefore needs insight into cost development and clear rules on which costs are reimbursable.

### What is the purpose of an incentive fee?

It gives the seller a reason to keep costs down or exceed performance targets. Buyer and seller share savings or overruns according to an agreed formula.

## Related terms

- [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract/)
- [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract-pmi/)
- [Time and materials contract](https://pmdecoder.com/en/glossary/time-and-materials-contract-pmi/)
- [Contract](https://pmdecoder.com/en/glossary/contract/)
- [Statement of work](https://pmdecoder.com/en/glossary/statement-of-work-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.