# Cost planning

also: Budget planning

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Setting costs by time and project component](https://pmdecoder.com/en/concept/setting-costs-by-time-and-project-component/)
- Topic area: [Cost and economic viability](https://pmdecoder.com/en/area/cost-and-economic-viability/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/cost-planning/

## Definition

Cost planning builds on the cost estimate and assigns the expected costs to work packages, cost types and time periods. The result is a time-phased cost plan showing when which funds are needed. Once approved, it serves as the baseline against which actual costs are compared, and as the basis for the organization's liquidity planning.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Cost management plan](https://pmdecoder.com/en/glossary/cost-management-plan/) | partially overlapping | denotes the plan containing the rules for estimating, budgeting and controlling costs |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Other terms

- Cost plan (related, not equivalent)
- Budget planning (synonym)

## Distinction

Cost estimation asks how much something will cost; cost planning asks when and where these costs will be incurred and how much will be released for them. Cost management additionally covers monitoring and control. Financial planning looks at cash flows, cost planning at the consumption of value; the two can diverge in time, for example with advance payments.

## In practice

A research consortium plans a three-year project with four partners. Cost planning distributes the estimated 2.4 million euros across partners, work packages and quarters. This reveals that expensive laboratory equipment has to be bought in the first half-year, whereas the grant money flows evenly over the term. The consortium therefore applies for an adjusted drawdown schedule before a small partner runs short of liquidity.

## Frequently asked questions

### What belongs in a cost plan?

Costs by work package and cost type, their distribution over time, reserves and the assumptions on which the values are based.

### How are the cost plan and the S-curve related?

The plan's costs accumulated over time form the S-curve, which is compared with actual costs as the project proceeds.

## Related terms

- [Cost estimation](https://pmdecoder.com/en/glossary/cost-estimation/)
- [Cost management](https://pmdecoder.com/en/glossary/cost-management/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [S-curve](https://pmdecoder.com/en/glossary/s-curve/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.