# Cost performance index

abbr. CPI

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Cost efficiency of work performed](https://pmdecoder.com/en/concept/cost-efficiency-of-work-performed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/cost-performance-index/

## Definition

The cost performance index describes the cost efficiency of a project as the ratio of earned value to actual cost. A value of 1.0 means that every euro spent has produced exactly one euro of planned work; 0.8 means only 80 cents. As a ratio, it allows projects of different sizes to be compared. It is also the basis of a widely used forecast: the total budget divided by the index gives the expected total cost if the efficiency achieved so far continues.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Cost performance index](https://pmdecoder.com/en/glossary/cost-performance-index-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Cost variance gives the difference in euros, the index the ratio. The schedule performance index measures progress against the plan, not costs. Analyses of many large projects suggest that a cost index well below one rarely improves fundamentally after the first third of a project.

## In practice

A plant manufacturer compares four ongoing projects of different sizes. The cost performance index is 1.02, 0.97, 0.95 and 0.78. Although the fourth project is the smallest, it receives the most attention: with a budget of 800,000 euros, it would cost around 1.03 million euros if its efficiency stayed the same. A review shows that a subcontractor is billing considerably more hours than calculated.

## Frequently asked questions

### How is the cost performance index calculated?

As earned value divided by actual cost, each cumulative up to the reporting date.

### What is a good cost performance index?

Values around 1.0 are considered on plan. Organizations often set thresholds, for example to look more closely from 0.95 and to escalate from 0.9.

## Related terms

- [Schedule performance index](https://pmdecoder.com/en/glossary/schedule-performance-index/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)
- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)

---