# Cost of quality

also: Quality costs · abbr. COQ

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Costs of prevention, appraisal and failure](https://pmdecoder.com/en/concept/costs-of-prevention-appraisal-and-failure/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/cost-of-quality/

## Definition

The cost of quality summarizes what a company or project spends on quality and on the lack of it. Prevention costs arise from training, quality planning or process improvements, appraisal costs from tests, inspections and audits. Failure costs are internal when defects are found before handover, for example as rework or scrap, and external when they only appear at the customer, for example through warranty claims, recalls or damage to reputation.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Cost of quality](https://pmdecoder.com/en/glossary/cost-of-quality-pmi/) | equivalent | — |
| Six Sigma | [Cost of Poor Quality](https://pmdecoder.com/en/glossary/cost-of-poor-quality/) | partially overlapping | Covers only the cost of poor quality, but explicitly includes hidden follow-on costs; prevention costs are not part of it. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The cost of quality is not the cost of a particularly high-grade execution, but the cost surrounding defects. A common distinction is made between the cost of conformance, that is prevention and appraisal, and the cost of non-conformance, that is failure costs. More recent approaches stress that investment in prevention usually lowers the total cost of quality.

## In practice

A manufacturer of household appliances evaluates the cost of quality of a product project. During development, tests and inspections cost 180,000 euros. After market launch, a faulty sealing ring causes warranty costs of 1.4 million euros. A post-project analysis shows that a three-month endurance test would have found the defect. For future projects this test becomes mandatory, even though it delays market entry.

## Frequently asked questions

### Why are external failure costs so high?

Because logistics, service, legal consequences and loss of trust come on top of fixing the defect. The later a defect is discovered, the more expensive it becomes.

### How can the cost of quality be reduced?

Above all through more prevention: clear requirements, early checks, suitable processes and training. More final inspections on their own usually just shift the costs.

## Related terms

- [Quality management](https://pmdecoder.com/en/glossary/quality-management/)
- [Rework](https://pmdecoder.com/en/glossary/rework/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action/)

---