# Cost management plan

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Setting costs by time and project component](https://pmdecoder.com/en/concept/setting-costs-by-time-and-project-component/)
- Topic area: [Cost and economic viability](https://pmdecoder.com/en/area/cost-and-economic-viability/)
- Canonical version: https://pmdecoder.com/en/glossary/cost-management-plan/

## Definition

In PMI usage, the cost management plan is a component of the project management plan and sets the rules by which costs in the project are estimated, budgeted, monitored and controlled. It specifies, for example, units of measure and rounding precision, the intended accuracy of estimates, the link to the organization’s chart of accounts through control accounts, variance thresholds beyond which action must be taken, and the rules of performance measurement, such as whether and how earned value management is used. Reporting formats and frequencies as well as responsibilities are added. The plan itself contains no cost figures; these are found in the budget and the cost baseline.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Cost planning](https://pmdecoder.com/en/glossary/cost-planning/) | partially overlapping | denotes the plan containing the rules for estimating, budgeting and controlling costs |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)

## Distinction

The concept of cost planning covers setting costs by time and project component. The cost management plan covers only part of it: it governs how this planning is done but does not provide its result. The figures themselves are found in the project budget and the cost baseline, and the processes in cost management as a whole.

## In practice

For an infrastructure project, the cost management plan specifies that costs are reported in thousands of euros without decimals, that every control account is mapped to a cost centre in financial accounting, and that percent complete is measured using the 0/50/100 rule. Deviations of more than ten percent in the cost performance index trigger a root cause analysis. When one trade falls below this value, it is immediately clear who has to act.

## Frequently asked questions

### Does the cost management plan contain the budget?

No. It describes rules and procedures. The budget and the cost baseline are separate results of cost planning, produced and updated according to these rules.

### Why are thresholds set in the cost management plan?

So that it is clear before the project starts what level of deviation requires a response and who triggers it. Without such limits, every deviation is renegotiated, or larger problems are noticed too late.

## Related terms

- [Cost planning](https://pmdecoder.com/en/glossary/cost-planning/)
- [Cost management](https://pmdecoder.com/en/glossary/cost-management/)
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Project budget](https://pmdecoder.com/en/glossary/project-budget-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)