# Corrective action

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Action against an occurred deviation](https://pmdecoder.com/en/concept/action-against-an-occurred-deviation/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/corrective-action-pmi/

## Definition

At PMI, a corrective action is a deliberately taken measure that brings project work performance back into line with the project management plan. It is prompted by an identified variance, such as a schedule delay or a cost overrun. The measure addresses the cause, not just the symptom, and its effect is checked afterwards. If it affects baselines or released results, it is submitted as a change request. In the process-based editions of the PMBOK Guide, it was one of the types of change request, alongside preventive action and defect repair.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/) | equivalent | — |

## Distinction

The PMI term is equivalent to “Korrekturmaßnahme” (corrective action) according to ISO 21506, which represents the concept in the glossary. A preventive action forestalls future variances; defect repair fixes a fault in a result. A workaround responds at short notice to a risk that has occurred and for which no response was planned.

## In practice

The earned value evaluation of a construction project shows that interior finishing is three weeks behind plan. The cause is a shortage of drywall workers. As a corrective action, the project manager engages a second subcontractor for two floors. After four weeks she checks whether the backlog has been cleared.

## Frequently asked questions

### When does a corrective action require a change request?

When it changes baselines, released deliverables or agreements. Measures within the project manager’s authority can be decided and documented by the project manager.

### How is the effect of a corrective action checked?

By measuring again the quantity that deviated, such as schedule or cost indicators. If there is no effect, the cause analysis was incomplete or the measure insufficient.

## Related terms

- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action-pmi/)
- [Change request](https://pmdecoder.com/en/glossary/change-request-pmi/)
- [Variance](https://pmdecoder.com/en/glossary/variance-pmi/)
- [Workaround](https://pmdecoder.com/en/glossary/workaround-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.