# Controlling a stage

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Concept: [Monitoring and controlling a project](https://pmdecoder.com/en/concept/monitoring-and-controlling-a-project/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/controlling-a-stage/

## Definition

Controlling a stage describes the ongoing work of the project manager within a management stage in PRINCE2. The project manager assigns work packages to teams, tracks their progress, receives completed work packages and regularly reviews the status of the stage. Issues and risks are captured and assessed. If deviations are within tolerance, the project manager takes corrective action; if a tolerance is forecast to be exceeded, the matter is escalated to the Project Board. Progress is reported at agreed intervals. The process is repeated in every stage after initiation.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Control](https://pmdecoder.com/en/glossary/control/) | partially overlapping | Control of a single stage by the Project Manager; Project Board decisions belong to other processes. |
| PM² | [Monitor & Control](https://pmdecoder.com/en/glossary/monitor-and-control/) | partially overlapping | Control of a single stage by the Project Manager; Project Board decisions belong to other processes. |

## Distinction

Control in the sense of ISO 21506 covers monitoring and controlling the whole project. Controlling a stage relates to a single stage and to the level of the project manager. The teams’ work on the products belongs to the process managing product delivery, and the decisions at the end of a stage belong to managing a stage boundary.

## In practice

In a stage to convert street lighting to LED, the project manager assigns three work packages to two installation firms. Every week he reviews the reported progress. When one firm falls behind because of supply shortages, he moves two streets to the other firm. This stays within tolerance, so no escalation is required.

## Frequently asked questions

### When does the project manager escalate to the Project Board?

When the forecast shows that a stage tolerance would be exceeded, or when a problem requires a decision beyond the project manager’s authority.

### Does the process apply to the initiation stage?

No. Initiation has its own process. Controlling a stage starts with the first stage after it.

## Related terms

- [Managing product delivery](https://pmdecoder.com/en/glossary/managing-product-delivery/)
- [Project Manager (PRINCE2)](https://pmdecoder.com/en/glossary/project-manager-prince2/)
- [Control](https://pmdecoder.com/en/glossary/control/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)
- [Work Package](https://pmdecoder.com/en/glossary/work-package-prince2/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.