# Control chart

also: Shewhart chart, Process control chart

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/control-chart/

## Definition

On a control chart, measured values or statistics from samples are plotted in time order. A centre line shows the average, and an upper and a lower control limit show the range within which a stable process usually varies; they are typically three standard deviations from the mean. Points outside the limits or conspicuous patterns within them indicate special influences. The method goes back to Walter A. Shewhart, who developed it in the 1920s.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Statistical process control](https://pmdecoder.com/en/glossary/statistical-process-control/)

## Distinction

Control limits derive from the process itself, specification limits from the requirements; a process can be stable and still produce scrap. The control chart monitors running processes, whereas a histogram shows the distribution of values without any time order. It helps to distinguish between common and special causes of variation.

## In practice

In a project introducing a new beverage filling line, the team monitors the fill volume with a control chart. Every thirty minutes, five bottles are weighed and the mean is plotted. After three days, seven consecutive points lie above the centre line, although all of them remain within the limits. The team interprets this as a shift in the process mean, checks the line and finds a weakening valve spring before any bottles are overfilled.

## Frequently asked questions

### What does a point outside the control limits mean?

That a special cause is probably at work. The process should be investigated before further defective results are produced.

### Which patterns other than points beyond the limits are suspicious?

For example, longer runs of points on one side of the centre line, steady rises or falls, and conspicuously regular fluctuations.

## Related terms

- [Control limit](https://pmdecoder.com/en/glossary/control-limit/)
- [Specification limit](https://pmdecoder.com/en/glossary/specification-limit/)
- [Common cause](https://pmdecoder.com/en/glossary/common-cause/)
- [Special cause](https://pmdecoder.com/en/glossary/special-cause/)
- [Quality control](https://pmdecoder.com/en/glossary/quality-control/)

---