# Control account

abbr. CA

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.14
- Edition: ISO 21506:2024
- Concept: [Management unit for scope, budget and schedule](https://pmdecoder.com/en/concept/management-unit-for-scope-budget-and-schedule/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/control-account/

## Definition

A control account is the level at which performance is measured and someone is held accountable for it. It is usually created where an element of the work breakdown structure intersects with an organizational unit from the organizational breakdown structure, and it contains one or more work packages. Each control account has a defined content, budget, schedule and responsible person; planned value, earned value and actual cost are compared and variances analysed at this level.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Control account](https://pmdecoder.com/en/glossary/control-account-pmi/) | equivalent | — |

## Distinction

A work package describes a defined piece of work, while a control account groups work packages into a unit that is reported on and controlled. It has nothing to do with an account in financial bookkeeping, even though actual costs are often captured through cost centres or project accounts and then assigned to it.

## In practice

A defence project divides the development of a radar system into 14 control accounts, such as "Antenna, hardware development" and "Antenna, testing". Each has a responsible manager who reports progress and costs every month. When the control account "Signal processing, software" shows a cost performance index of 0.82, its manager has to explain the causes and submit a new estimate to complete. The other accounts are not affected.

## Frequently asked questions

### How many control accounts does a project need?

As many as are needed for meaningful accountability and control. Too few hide problems in large totals; too many create reporting effort without adding insight.

### Who is responsible for a control account?

Usually a person from the line organization or the project team who can make decisions about the work in the account. They plan the work packages, report progress and explain variances.

## Related terms

- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Undistributed budget](https://pmdecoder.com/en/glossary/undistributed-budget/)

---