# Control account

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Management unit for scope, budget and schedule](https://pmdecoder.com/en/concept/management-unit-for-scope-budget-and-schedule/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/control-account-pmi/

## Definition

At PMI, a control account is the point in the project where the content of the work, its budget, the costs already incurred and the dates are brought together and compared with earned value to judge performance. It sits at a selected point of the work breakdown structure, above the work packages, and comprises one or more work packages, each of which belongs to only one control account. Each control account has a responsible person, often called the control account manager. Where control accounts are placed depends on the size and risk of the project and on the organizational structure.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Control account](https://pmdecoder.com/en/glossary/control-account/) | equivalent | — |

## Distinction

The term “Control Account” according to ISO 21506, which represents the concept in the glossary, is equivalent; both standards use the same English term. A work package is the smallest planned unit of work; the control account is the level at which performance is measured and owned. It should not be confused with a cost centre in accounting.

## In practice

In the construction of a logistics centre, the general contractor sets up control accounts for the shell, roof and facade, building services and external works. Each has a responsible site manager. Every month, planned value, earned value and actual cost are compared for each control account; when thresholds are exceeded, the responsible person explains the variance.

## Frequently asked questions

### At what level should a control account be placed?

High enough for the reporting effort to remain manageable, and low enough for variances to be detected early and attributed to a responsible person. There is no fixed rule.

### Can a work package belong to several control accounts?

No. Each work package belongs to exactly one control account; otherwise budget, cost and performance could not be assigned unambiguously.

## Related terms

- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)
- [Code of accounts](https://pmdecoder.com/en/glossary/code-of-accounts/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.