# Continued business justification

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Grundprinzipien
- Edition: PRINCE2 7
- Concept: [Economic justification of an initiative](https://pmdecoder.com/en/concept/economic-justification-of-an-initiative/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/continued-business-justification/

## Definition

Continued business justification is one of the seven PRINCE2 principles. It requires that there is a valid reason for the project at all times: the expected benefits must justify the costs, effort and risks, and the project must fit the objectives of the commissioning organization. The justification is not checked once at the start and then forgotten; it is kept up to date and reassessed at the end of every stage. If it no longer holds, for example because market conditions, costs or priorities have shifted, the project should be adjusted or closed early. The justification is documented in the business case, which is owned by the Executive.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Business case](https://pmdecoder.com/en/glossary/business-case/) | partially overlapping | Principle of reviewing the justification throughout the project; the document itself is the business case. |
| PMI / PMBOK Guide | [Business case](https://pmdecoder.com/en/glossary/business-case-pmi/) | partially overlapping | Principle of reviewing the justification throughout the project; the document itself is the business case. |

## Distinction

The business case is the document that records the justification; the principle is the commitment to keep reviewing it. Many organizations assess a project economically only when it is approved. PRINCE2 differs by making that assessment recurrent. Even compulsory projects, such as those needed to meet legal requirements, need a justification under this principle, for instance a comparison of several options for meeting the obligation.

## In practice

An insurer is building a new customer portal. At the end of the second stage it emerges that a competitor offers a similar platform as a subscription service that costs a fraction of the remaining development budget. The project manager updates the business case, and the Project Board decides to stop the in-house build and to reuse the requirements already written to select the subscription service.

## Frequently asked questions

### Has a project that is closed early failed in PRINCE2 terms?

Not necessarily. If the justification has disappeared, an orderly closure is a responsible decision, because continuing would tie up money and people without sufficient return.

### When is the business justification reviewed?

Mainly before the project starts, at the end of initiation and at every boundary between management stages, and also whenever an exception affects the basis of the project.

## Related terms

- [Business case](https://pmdecoder.com/en/glossary/business-case/)
- [Business case](https://pmdecoder.com/en/glossary/business-case-pmi/)
- [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)
- [Manage by stages](https://pmdecoder.com/en/glossary/manage-by-stages/)
- [Business Case](https://pmdecoder.com/en/glossary/business-case-prince2/)
- [Business case practice](https://pmdecoder.com/en/glossary/business-case-practice/)