# Contingency reserve

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Allowance for known risks](https://pmdecoder.com/en/concept/allowance-for-known-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/contingency-reserve/

## Definition

In PMI usage, the contingency reserve is an amount of time or money provided within the schedule baseline or cost baseline for identified risks. It covers the so-called known unknowns: risks that have been identified and assessed and for which the team has planned a response or deliberately chosen acceptance. The amount may be set as a percentage, as a fixed sum or on the basis of quantitative analyses such as expected monetary value or Monte Carlo simulation. Because the reserve is part of the baseline, the project manager controls it within the agreed rules. If risks no longer apply, the associated reserve can be reduced; if a new risk emerges, it can be adjusted.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The contingency reserve corresponds to the Risikoreserve of ISO 21506. It differs from the management reserve in subject and authority: the contingency reserve relates to known risks and is part of the baseline, while the management reserve covers the unforeseen, lies outside the baseline and is released by management.

## In practice

In the renovation of an old building, three risks are particularly relevant: pollutants in the insulation, damage to timber beams and delays at the heritage authority. The team assesses them with expected monetary value and sets a contingency reserve of 95,000 euros and three weeks. When the beams turn out to be sound, the share intended for them is removed from the reserve after consultation with the sponsor.

## Frequently asked questions

### Who may use the contingency reserve?

Usually the project manager, within the rules set out in the project management plan, because the reserve is part of the baseline. Many organizations nevertheless require documentation of the risk for which it was used.

### How large should the contingency reserve be?

That depends on the number and weight of the identified risks and on the organization’s risk appetite. Flat percentages are simple, but deriving the amount from the risk analysis is easier to justify.

## Related terms

- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)
- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve-pmi/)
- [Project budget](https://pmdecoder.com/en/glossary/project-budget-pmi/)
- [Contingency plan](https://pmdecoder.com/en/glossary/contingency-plan-pmi/)
- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)

---