# Contingency plan

also: Contingent response

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Pre-planned response to an occurring risk](https://pmdecoder.com/en/concept/pre-planned-response-to-an-occurring-risk/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/contingency-plan/

## Definition

A contingency plan is ready before it is needed. It describes what exactly will be done when a particular risk occurs, who acts, what resources are available and how the occurrence is recognized. This trigger, such as a missed date or a measured value, is defined in advance so that there is no need for discussion when the situation arises.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Contingency plan](https://pmdecoder.com/en/glossary/contingency-plan-pmi/) | closely related | denotes the plan with its triggers, the contingency response the reaction itself |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Preventive actions take effect before the risk occurs and are intended to prevent it; contingency plans take effect afterwards and are intended to limit the damage. A workaround, by contrast, is an unplanned reaction to a problem for which nothing had been prepared. A fallback plan comes into play if the contingency plan does not work either.

## In practice

For the switchover of a supermarket chain's checkout system on a Sunday, there is a contingency plan: if the new system is not working in a branch at six o'clock on Monday morning, the old system, which remains installed in parallel for two more weeks, is switched back on there. The regional IT coordinator is responsible, and the trigger is a failed test purchase. The plan is invoked in two of 80 branches, and all of them open on time.

## Frequently asked questions

### For which risks are contingency plans prepared?

For risks with a significant impact that cannot be adequately prevented, and for accepted risks where quick action would be needed if they occurred.

### What is a trigger?

A signal defined in advance that indicates that a risk is occurring or is imminent and that sets the prepared response in motion.

## Related terms

- [Workaround](https://pmdecoder.com/en/glossary/workaround/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.