# Configuration management

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.12
- Edition: ISO 21506:2024
- Concept: [Managing components and versions of a result](https://pmdecoder.com/en/concept/managing-components-and-versions-of-a-result/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/configuration-management/

## Definition

Configuration management specifies which components of a product, a facility or a set of documentation are managed as configuration items, and records their versions and relationships. It includes identifying these items unambiguously, controlling changes to them, recording their current status and regularly checking whether documentation and the actual result still match.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Configuration management system](https://pmdecoder.com/en/glossary/configuration-management-system/) | closely related | denotes the set of rules with procedures and tools, not the activity itself |
| PRINCE2 | [Product Register](https://pmdecoder.com/en/glossary/product-register/) | partially overlapping | Record of products with version and status on which configuration management relies. |

## Distinction

Change management decides whether a change is made; configuration management ensures that afterwards all documents and components consistently reflect the new status. Version control in software development is a tool of configuration management, not the same thing. Guidance is provided by ISO 10007.

## In practice

A special-purpose machine builder supplies packaging lines adapted to each customer. After a service call, it turns out that one line at a customer site is running different control software from what the documentation states. The company then introduces a configuration list for every line, with assemblies, drawing revisions and software versions. Every change made during commissioning or servicing has to be entered there before the order can be closed.

## Frequently asked questions

### What is a configuration item?

A component that is identified, versioned and changed in its own right, such as an assembly, a software module or a document.

### Do small projects need configuration management?

In simplified form, yes, as soon as several versions of a result are in circulation. Clear version numbers and well-kept filing are often enough.

## Related terms

- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.