# Communication plan

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.11
- Edition: ISO 21506:2024
- Concept: [Arrangements for project communication](https://pmdecoder.com/en/concept/arrangements-for-project-communication/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/communication-plan/

## Definition

The communication plan turns what stakeholders need to know into specific arrangements. For each measure it names the content, target group, sender, timing or frequency, channel and format. It is usually set out as a table, drawn up at the start of the project and adjusted when the project environment changes.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Communications management plan](https://pmdecoder.com/en/glossary/communications-management-plan/) | closely related | additionally covers rules, methods and responsibilities for all communication |
| PRINCE2 | [Communication Management Approach](https://pmdecoder.com/en/glossary/communication-management-approach/) | closely related | Same purpose; as a management product part of the project initiation documentation and closely linked to the defined reports. |

## Distinction

The communication plan is a planning document, project communication is what actually happens. Stakeholder analysis provides the basis by showing who has which interests and how much influence. It differs from a reporting plan, which only governs formal reports, in that it covers all communication channels.

## In practice

For the introduction of a new shift model in a logistics centre, the project team draws up a communication plan with 18 measures. The works council and managers are involved before every decision, and employees get a staff meeting and a notice in three languages after each project phase. When a pilot shift has to be postponed, the plan immediately shows who needs to be informed and in what order. Nobody hears the news second-hand.

## Frequently asked questions

### What should a communication plan contain as a minimum?

The target group, content, responsible person, timing or frequency and channel of each measure.

### Does the communication plan also cover confidentiality?

It should record which information is confidential and only goes to certain recipients, such as personnel data or contract details.

## Related terms

- [Project communication](https://pmdecoder.com/en/glossary/project-communication/)
- [Stakeholder management](https://pmdecoder.com/en/glossary/stakeholder-management/)
- [Project reporting](https://pmdecoder.com/en/glossary/project-reporting/)

---