# Communication Management Approach

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Managementprodukte
- Edition: PRINCE2 7
- Concept: [Arrangements for project communication](https://pmdecoder.com/en/concept/arrangements-for-project-communication/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/communication-management-approach/

## Definition

The communication management approach describes how a PRINCE2 project communicates with its stakeholders. It builds on an analysis of those involved and affected and records what information they need, who provides it, at what frequency and through which channels. This includes communication within the project organization, such as reports to the project board, and externally, for example to customers, authorities or the public. The approach is created during initiation, becomes part of the project initiation documentation and is reviewed at stage boundaries, because the circle of stakeholders can change over time.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Communication plan](https://pmdecoder.com/en/glossary/communication-plan/) | closely related | Same purpose; as a management product part of the project initiation documentation and closely linked to the defined reports. |
| PMI / PMBOK Guide | [Communications management plan](https://pmdecoder.com/en/glossary/communications-management-plan/) | closely related | additionally covers rules, methods and responsibilities for all communication |

## Distinction

The communication plan under ISO 21506 and the PMI communications management plan serve the same purpose. The differences lie in how it is embedded: in PRINCE2 the approach is one management product among others and is closely linked to the defined reports. The reports themselves are separate management products.

## In practice

A municipality is refurbishing a main road. The communication management approach provides for residents to be informed by leaflet fourteen days before each closure, for local businesses to attend a monthly round table and for the municipal council to receive a short report each quarter. The project board receives a status report from the project manager every two weeks.

## Frequently asked questions

### Who prepares the communication management approach?

Usually the project manager, with help from project support. The project board reviews and approves it as part of the project initiation documentation.

### Does it need to be adjusted after initiation?

Often, yes. If new stakeholders appear or their expectations change, the approach is revised at the latest when moving into the next stage.

## Related terms

- [Organizing practice](https://pmdecoder.com/en/glossary/organizing-practice/)
- [Communication plan](https://pmdecoder.com/en/glossary/communication-plan/)
- [Communications management plan](https://pmdecoder.com/en/glossary/communications-management-plan/)
- [Project communication](https://pmdecoder.com/en/glossary/project-communication/)
- [Stakeholder](https://pmdecoder.com/en/glossary/stakeholder/)
- [Project Initiation Documentation](https://pmdecoder.com/en/glossary/project-initiation-documentation/)
- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)

---