# Closing a project

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Concept: [Closing stage of a project](https://pmdecoder.com/en/concept/closing-stage-of-a-project/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/closing-a-project/

## Definition

Closing a project provides PRINCE2 with a fixed end point at which it is checked whether the objectives have been achieved. The process takes place at the end of the final stage, either as planned or prematurely if the Project Board orders the project to stop. The project manager ensures that the products have been accepted and handed over to the operational organization, evaluates the project against its objectives, secures the lessons and makes sure that the review of benefits after the project is planned. Finally, the project manager recommends closure to the Project Board, which confirms it and releases the resources.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | [Closing Phase](https://pmdecoder.com/en/glossary/closing-phase-pm2/) | closely related | fixed phase after the Ready for Closing phase gate, with the Project-End Report |
| Six Sigma | [Control phase](https://pmdecoder.com/en/glossary/control-phase/) | closely related | Closes the project, but focuses on securing the improvement for the long term and handing it over to the process owner. |
| cross-framework | [Project closure](https://pmdecoder.com/en/glossary/project-closure/) | closely related | Process within the final stage rather than a stage of its own; also used for premature closure. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The closing phase in PM² and general project closure cover similar tasks. PRINCE2 places closure as a process within the final stage rather than as a stage of its own. Reviewing the benefits, which often arise only later, remains a task for the commissioning organization after the project has ended.

## In practice

After a new ticketing system has been introduced in customer service, the project manager hands over the system, documentation and open issues to IT operations. She compares costs and dates with the plan, notes that training started too late and plans a benefits review after six months with the Executive. The Project Board then confirms closure.

## Frequently asked questions

### How does premature closure work?

Much like planned closure, but with an emphasis on securing completed and partly completed products and recording what is still missing, so that later work can build on it.

### Does responsibility for benefits end with project closure?

No. Many benefits arise only after the project. Their review is planned before closure and carried out afterwards by the commissioning organization.

## Related terms

- [Project closure](https://pmdecoder.com/en/glossary/project-closure/)
- [Closing Phase](https://pmdecoder.com/en/glossary/closing-phase-pm2/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/)
- [Learn from experience principle](https://pmdecoder.com/en/glossary/learn-from-experience-principle/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)
- [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/)
- [Lessons Report](https://pmdecoder.com/en/glossary/lessons-report/)
- [Benefits Management Approach](https://pmdecoder.com/en/glossary/benefits-management-approach/)

---