# Change request

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.10
- Edition: ISO 21506:2024
- Concept: [Formal request to change what was agreed](https://pmdecoder.com/en/concept/formal-request-to-change-what-was-agreed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/change-request/

## Definition

A change request sets out, in a form that can be examined, a desired change to the scope, schedule, cost, quality or approach of a project or programme. It describes what is to be changed and why, and is supplemented by an assessment of the effects. Only the decision of the responsible body turns the proposal into an approved change; until then the existing baseline applies. Requests can also concern corrections or preventive actions, not only new wishes.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Change request](https://pmdecoder.com/en/glossary/change-request-pmi/) | equivalent | — |

## Distinction

The change request is the individual document, the change register the overview of all requests, and change control the process in which they are assessed and decided. A contract variation governs the contractual and financial consequences of a change between client and contractor and may be based on an approved change request.

## In practice

In a project to introduce HR software, the payroll department wants an additional report on travel expenses. Instead of asking the developers directly, it submits a change request. The project manager estimates twelve person-days of effort and a one-week delay to testing; the budget remains unchanged because a report originally planned is dropped in exchange. The change control board approves the request, the change register is updated and the schedule adjusted.

## Frequently asked questions

### Who may submit a change request?

In principle any stakeholder can propose a change, including the sponsor, users or team members. What matters is that the request goes through the agreed route and is not implemented by bypassing project control.

### What does a change request contain?

A description of the requested change and its justification, together with an assessment of its effects on scope, schedule, cost, quality and risks. Information on urgency and on the consequences of not making the change is also helpful.

### Who decides on a change request?

This is set out in the project’s change management. Smaller changes within agreed limits are often decided by the project manager, larger ones by the sponsor or a dedicated change control board.

## Related terms

- [Change register](https://pmdecoder.com/en/glossary/change-register/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Project scope](https://pmdecoder.com/en/glossary/project-scope/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.