# Change request

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Formal request to change what was agreed](https://pmdecoder.com/en/concept/formal-request-to-change-what-was-agreed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/change-request-pmi/

## Definition

At PMI, a change request is a formal request to change a project document, a deliverable or a baseline. It describes what is to be changed, why, and what impact on scope, schedule, cost, quality and risks is expected. Change requests go through change control and are recorded in the change log. In the process-based editions, PMI assigned several types to change requests: corrective action, preventive action, defect repair and updates to documents or plans. In principle, any stakeholder can submit one.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Change request](https://pmdecoder.com/en/glossary/change-request/) | equivalent | — |

## Distinction

The PMI term is equivalent to “Änderungsantrag” (change request) according to ISO 21506, the lead term of the concept in the glossary. A change request is not the change itself but the request for it. An issue describes a problem that has occurred; whether it leads to a change request depends on the chosen solution.

## In practice

While a trade fair stand is being built, the customer asks for a larger video wall. The project manager records a change request with the supplier’s quotation, additional power connections and one extra day for assembly. The customer approves the additional costs in writing, and the order with the supplier is amended.

## Frequently asked questions

### Who may submit a change request?

In principle, any stakeholder. What matters is that the request is fully documented and assessed and decided through the defined process rather than implemented on demand.

### Is a corrective action also a change request?

In PMI’s understanding it can be. If a corrective action requires intervention in baselines or released results, it is submitted and decided as a change request.

## Related terms

- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action-pmi/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action-pmi/)
- [Change register](https://pmdecoder.com/en/glossary/change-register/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.