# Change register

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.9
- Edition: ISO 21506:2024
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/change-register/

## Definition

The change register records every change that comes up in the project or programme, from the first suggestion to implementation or rejection. Each entry usually includes an identifier, a short description, its origin and date, the assessed effects on scope, schedule, cost and risks, the decision with its date and decision-maker, and the current status. This keeps it traceable how the undertaking has changed compared with the original plan.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A change request is the individual document that proposes a particular change; the change register is the overview of all of them. Change control is the process in which requests are assessed and decided. The register differs from the revision history of a single document in that it relates to the undertaking as a whole.

## In practice

After six months, a project to introduce HR software has 47 changes recorded in its register: 29 approved, 11 rejected, 7 still being assessed. While preparing for the steering committee, the team notices that the approved changes add up to 38 person-days of extra effort, even though each one was small. The committee decides to decide on changes in monthly batches from now on and to update the baseline for the extra effort.

## Frequently asked questions

### Who maintains the change register?

Usually the project manager or the project office. What matters is that every suggestion is recorded before it is implemented, even if it is later rejected.

### Do rejected changes belong in the register?

Yes. They in particular show later which requests were considered and why they were not implemented, and they prevent the same discussion from starting again.

## Related terms

- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board/)
- [Configuration management](https://pmdecoder.com/en/glossary/configuration-management/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)

---