# Change control

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Controlled handling of changes](https://pmdecoder.com/en/concept/controlled-handling-of-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/change-control-pmi/

## Definition

At PMI, change control is the process in which proposed changes to project documents, deliverables or baselines are recorded, assessed for their impact and then approved, rejected or deferred. The decision is documented, and approved changes are implemented and tracked. In the predictive approach, PMI treated this control across all components of the plan, so that a change in scope, for instance, is also reflected in schedule, cost, risks and quality. How strict the process is and who decides are defined in the project management plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Issues practice](https://pmdecoder.com/en/glossary/issues-practice/) | closely related | Covers not only change requests but also deviations from specification, problems and concerns. |
| cross-framework | [Change control](https://pmdecoder.com/en/glossary/change-control/) | closely related | emphasizes the review of and decision on change requests, less their implementation |
| PRINCE2 | [Issue Management Approach](https://pmdecoder.com/en/glossary/issue-management-approach/) | partially overlapping | Document setting out the rules for issues and changes in one project, not the activity itself. |

## Distinction

Across frameworks, “Änderungsmanagement” (change management) stands for the concept; the PMI term is closely related. Change control emphasizes the formal assessment and decision process, whereas change management in general usage can be broader. Organizational change management, meaning guiding people through change, is something else.

## In practice

In a project for a customer portal, the business unit asks for an additional export function. The project manager has the request recorded as a change request and assessed by the team: three weeks of extra effort, no impact on go-live, but a higher testing risk. The change control board approves the change, the baselines are adjusted and the change log is updated.

## Frequently asked questions

### Does every change have to go through change control?

Only changes to items under change control, above all baselines and released deliverables. The project management plan defines which changes the project manager may decide alone.

### How does change control fit adaptive approaches?

In adaptive approaches, changes are usually absorbed through ongoing prioritization of the backlog. Formal change control applies there mainly to contractual conditions, budget or fundamental decisions.

## Related terms

- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change request](https://pmdecoder.com/en/glossary/change-request-pmi/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline-pmi/)
- [Configuration management system](https://pmdecoder.com/en/glossary/configuration-management-system/)
- [Change register](https://pmdecoder.com/en/glossary/change-register/)

---