# Change control board

also: Change board · abbr. CCB

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Body deciding on changes](https://pmdecoder.com/en/concept/body-deciding-on-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/change-control-board/

## Definition

A change control board concentrates the decisions on changes that go beyond the authority of the project manager. Its members are usually representatives of the sponsor, the project manager, affected departments and, where relevant, contractors. It meets regularly or as required, assesses change requests on the basis of prepared impact analyses and records its decisions in writing.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/) | equivalent | — |
| PRINCE2 | [Change Authority](https://pmdecoder.com/en/glossary/change-authority/) | closely related | Can also be a single person; authority derived from and limited by the Project Board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The steering committee directs the project as a whole, the change control board deals only with changes; in smaller projects the steering committee takes on this task as well. In IT operations there are comparable bodies for changes to live systems that work independently of projects. Change control is the procedure; the board is one decision-making body within it.

## In practice

During the renewal of a public transport operator's control system, change requests from operations, engineering and safety converge. A change control board meets every two weeks. Every request must first be assessed by the affected subprojects, otherwise it is deferred. Within one year the board handles some eighty requests. The decision log later serves at acceptance as evidence of why the system deviates from the original requirements specification.

## Frequently asked questions

### Who should sit on the change control board?

People who can assess impacts and take binding decisions, typically the sponsor, the project manager and those responsible for the affected areas.

### What happens to urgent changes?

An expedited procedure should be defined for emergencies, for example a decision by two named members with subsequent confirmation by the board.

## Related terms

- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Delegated authority](https://pmdecoder.com/en/glossary/delegated-authority/)

---