# Change control board

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Body deciding on changes](https://pmdecoder.com/en/concept/body-deciding-on-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/change-control-board-pmi/

## Definition

At PMI, the change control board, abbreviated CCB, is a formally constituted body that examines proposed changes to the project and decides whether to approve, defer or reject them. All decisions are recorded and communicated to those affected. Composition, authority and meeting frequency are defined in the project management plan. Typical members are the sponsor or client, user representatives, the project manager and those responsible for business and technical matters. Minor changes may often be decided below the CCB.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Change control board](https://pmdecoder.com/en/glossary/change-control-board/) | equivalent | — |
| PRINCE2 | [Change Authority](https://pmdecoder.com/en/glossary/change-authority/) | closely related | Can also be a single person; authority derived from and limited by the Project Board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The PMI term is equivalent to “Änderungsausschuss” (change board), the cross-framework lead term of the concept in the glossary. A steering committee directs the project as a whole; in some organizations it also takes on the role of the CCB. Change control refers to the process, the CCB to the body that decides within it.

## In practice

In a project to modernize a signal box, the CCB meets every two weeks. Its members are the client’s representative, the project manager, the safety officer and the head of commissioning. Changes of up to two working days of effort are decided by the project manager alone and reported to the CCB at its next meeting.

## Frequently asked questions

### Does every project need a change control board?

No. In small projects the sponsor and project manager often decide together. A dedicated body is worthwhile when there are many participants, contractual commitments or safety-critical results.

### What does the CCB need to make a decision?

A complete change request with a description, justification and assessed impact on scope, schedule, cost, quality and risks, ideally with alternatives.

## Related terms

- [Change control board](https://pmdecoder.com/en/glossary/change-control-board/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)
- [Change request](https://pmdecoder.com/en/glossary/change-request-pmi/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee-pmi/)
- [Sponsor](https://pmdecoder.com/en/glossary/sponsor-pmi/)

---