# Change Authority

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Body deciding on changes](https://pmdecoder.com/en/concept/body-deciding-on-changes/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/change-authority/

## Definition

The Change Authority in PRINCE2 is a person or group to whom the Project Board delegates decisions on certain changes. This covers requests for change and cases in which a product does not meet its agreed specification. The Project Board defines the scope within which the Change Authority may decide and often provides a dedicated change budget. Larger changes remain reserved for the Project Board. If no Change Authority is appointed, the Project Board decides itself. Where many changes are expected, the role relieves the board and speeds up decisions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/) | closely related | Can also be a single person; authority derived from and limited by the Project Board. |
| cross-framework | [Change control board](https://pmdecoder.com/en/glossary/change-control-board/) | closely related | Can also be a single person; authority derived from and limited by the Project Board. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A change board in the general sense and the change control board in PMI publications are bodies that decide on changes. The Change Authority is similar but can also be a single person, and its authority is expressly derived from, and limited by, the Project Board. Change management refers to the whole procedure; the Change Authority is only the decision-making point within it.

## In practice

On a project for a new customer platform, the Project Board expects many small requests for adjustments. It appoints the Senior User as Change Authority for changes of up to five person-days and provides a budget of 60 person-days for this. Larger requests and changes that threaten the deadline still go to the Project Board.

## Frequently asked questions

### Can the Project Manager be the Change Authority?

Yes, for small changes within clearly set limits. The Project Board should, however, set the limits so that significant decisions remain with it.

### What is a change budget?

An amount reserved for approved changes. The Change Authority can fund changes from it without involving the Project Board each time.

## Related terms

- [Change control board](https://pmdecoder.com/en/glossary/change-control-board/)
- [Change control board](https://pmdecoder.com/en/glossary/change-control-board-pmi/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Change request](https://pmdecoder.com/en/glossary/change-request/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)
- [Issues practice](https://pmdecoder.com/en/glossary/issues-practice/)
- [Issue Report](https://pmdecoder.com/en/glossary/issue-report/)
- [Organizing practice](https://pmdecoder.com/en/glossary/organizing-practice/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.