# Burndown chart

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Chart of remaining work over time](https://pmdecoder.com/en/concept/chart-of-remaining-work-over-time/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/burndown-chart/

## Definition

In PMI usage a burndown chart plots the work still to be done in a timebox against the time remaining. The horizontal axis shows time, for example the days of an iteration; the vertical axis shows the outstanding work, measured for instance in story points, hours or number of tasks. An ideal line shows how the remaining work would fall with steady progress; the actual line is updated regularly, usually daily. If it lies well above the ideal line, the team is at risk of missing its goal for the timebox. The chart serves mainly the team’s self-management and transparency towards stakeholders.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Burn-down chart](https://pmdecoder.com/en/glossary/burn-down-chart/) | equivalent | — |

## Distinction

The cross-framework term burn-down chart refers to the same diagram. A burnup chart instead shows the work already completed and makes changes to the overall scope visible, which appear as unexplained jumps in a burndown chart. Unlike an S-curve from earned value analysis, the burndown chart does not depict costs.

## In practice

A team has planned 40 story points for a two-week iteration. After six working days the burndown chart still shows 32 open points, while the ideal line is at 16. In the daily coordination meeting it emerges that an interface is blocked. The team brings in a colleague and discusses with the person responsible for the product which story could be dropped if necessary.

## Frequently asked questions

### In what unit is remaining work measured?

The team decides. Story points, estimated hours or the number of open tasks are common. What matters is not to change the unit within a timebox.

### Can a burndown chart be used for whole releases?

Yes, as a release burndown across several iterations. There, however, scope changes more often, which is why many teams prefer a burnup chart for longer periods.

## Related terms

- [Burn-down chart](https://pmdecoder.com/en/glossary/burn-down-chart/)
- [Timebox](https://pmdecoder.com/en/glossary/timebox/)
- [Iteration](https://pmdecoder.com/en/glossary/iteration-pmi/)
- [Story point](https://pmdecoder.com/en/glossary/story-point-pmi/)
- [Sprint Backlog](https://pmdecoder.com/en/glossary/sprint-backlog/)

---